Laytime normally cannot start until a valid notice of readiness has been tendered. A NOR tendered too early, or before the vessel is truly ready, can move the start of laytime by hours or days.

The vessel must have arrived

Under a berth charter the vessel arrives at the berth. Under a port charter it arrives when it reaches the place in the port where ships usually wait. Clauses such as WIBON (whether in berth or not), WIPON (whether in port or not), WIFPON (whether in free pratique or not) and WCCON (whether customs cleared or not) let the NOR be tendered earlier than it otherwise could.

The vessel must be ready

Ready means physically ready to load or discharge (holds clean, gear working) and legally ready, unless the clause says otherwise. Many charter parties also say when and how the NOR may be tendered: office hours, by email, or not before the laycan opens.

What an invalid NOR does

Under English law an invalid NOR is generally treated as having no effect, and it does not become valid later just because the vessel becomes ready. Laytime may then start only on a fresh, valid notice, or when cargo work begins if the charterers are taken to have accepted the ship without one. The charter party wording and the facts decide which applies.

Common Questions

Does the charterer accepting the NOR make it valid?

Not always. Signing an NOR 'as received' or without comment is different from accepting it. Many statements are argued over exactly this point, so keep the email and the SOF entry that show what happened.

How long after NOR does laytime start?

Most charter parties give a notice time, often 6 or 12 hours after a valid NOR, or a start at a fixed hour after tender. That gap is part of the laytime clause, not the NOR itself.